Home
Judicial Advocacy
|
Judicial Advocacy
TEN MURDER CLAUSES IN SUBCONTRACTS:
Although any language in a contract can be deadly and
should be viewed with caution, the following clauses can be particularly
lethal if not handled with care.
-
INCORPORATION BY REFERENCE. This
provision incorporates the general contractors agreement with the
owner by reference into the agreement between the general contractor
and the subcontractor.
-
THE CONTINGENCY PAYMENT CLAUSES.
This clause provides that the general contractor is under no
obligation to pay the subcontractor any sums due until such time as
the general contractor receives payment from the owner. (In June
of 1997 this clause was declared void and unenforceable by the
California Supreme Court.)
-
NO DAMAGE FOR DELAY. Customarily,
this provision provides that while the subcontractor is not entitled
to a claim for delay damages, it will be entitled to an extension of
time. Many times a contract will provide that the subcontractor
is entitled to no damages for delay but, on the other hand, the
contractor is entitled to liquidated damages for any delay caused by
the subcontractor.
-
DISPUTE RESOLUTION. Many contracts
provide that the architect is the judge, jury and executioner with
regards to any dispute between the owner, contractor and
subcontractor. This is particularly true with the new AIA
contract.
-
AGREEMENT TO CONTINUE WORK IN THE FACE OF A
DISPUTE. The agreement to continue work after a dispute
has arisen and not stop work is an absolute prescription for
bankruptcy unless you can afford to finance the entire project without
a progress payment.
-
ATTORNEY'S FEES. To recover
attorney's fees in any litigation, California law requires that a
written contract which provides for recover of attorney's fees be
entered into between the parties. If an attorney's fee provision
is not contained within the contract, neither party to the litigation
can recover them.
-
PROTECTION OF WORK, PERSONS & PROPERTY.
Subcontractor is required to "promptly remedy any loss or damage
caused to the work, materials, equipment and property" on or
about the project even if only partially attributable to the
subcontractors work. Are you a builder or an insurer?
-
RETENTION PROVISIONS. Retention,
contrary to popular belief, should not be the owners contingent
financing to complete the project nor the general contractors
bargaining tool to negotiate a settlement on other projects, which it
is working with the subcontractor. The traditional "ten
percent retention" which is claimed by most contractors and
owners to be the "industry standard" is a myth and should be
negotiated on every contract.
-
INDEMNIFICATION. You should only
be responsible for your own wrongs.
-
PROMPT PAY WAIVER. The new
Business & Professions Code §7108.5 provides that a prime
contractor must pay the subcontractor within 10 days of payment by the
owner. The penalty for non-compliance is 2% per month plus court
costs and attorneys fees.
Although the foregoing list of contract clauses is not all
inclusive, it does attempt to set out those areas which have proven to be
most troublesome to subcontractors and ultimately to suppliers who look to
them for payment. (Revised 11/00)
American Subcontractors Association
California, Inc.
P.O. Box 292867, Sacramento, California 95829-2867
Phone: 888-310-2722 Fax: 530-662-2865
e-mail |
©1999-2007, American Subcontractors
Association of California. Reproduction
of images or content belong to ASAC and may not
be borrowed, used or taken in any form whatsoever without written
permission.
Updated on:August 01, 2007 11:40 PM
Website by Wolven
CyberArts. |
|