California Lien Laws
An
Overview of
Mechanic Liens and Stop Notice Remedies
A properly filed and foreclosed Mechanic’s Lien gives the claimant a security interest in the property itself. If the Mechanic’s Lien claimant prevails at trial, the court will order the sale of the property on which the lien claimant performed work or supplied materials in order to pay off the lien claimant.
A properly served and
perfected Stop Notice gives the claimant a lien against
undisbursed construction funds in the possession of either
the owner or the lender. For private works of improvement,
the Mechanic’s Lien and Stop Notice gives the claimant a
lien against undisbursed construction funds in the
possession of either the owner or the lender.
A properly served and perfected claim on a payment bond gives the claimant the right to recover the amount owed from the surety that issued the bond.
For private works of
improvement, the Mechanic’s Lien and Stop Notice are
cumulative remedies which can be simultaneously pursued
along with a suit for breach of contract on the underlying
debt. Generally, a Mechanic’s Lien cannot be filed on a
publicly owned parcel of real property. On
An understanding of Mechanic’s Lien, Payment Bond and/or Stop Notice procedures can greatly increase the chances of eventual collection by the subcontractor or supplier. The Lien and Stop Notice laws are extremely technical and even the smallest failure to take the proper steps, at the proper time and in the proper order, can result in the complete loss of the claimant's Mechanic’s Lien and Stop Notice rights. It should be noted that even if these remedies are lost, the unpaid contractor may still sue the party with whom it contracted for the amount owed. The following chart sets forth the various remedies:
|
Action |
Parties to Action |
Remedy |
Limitation Period |
|
Breach of Contract |
Whomever you contracted with |
Money judgment |
Written Contract 4 years |
|
|
|
|
Oral Contract 2 years |
|
Common counts |
Whomever you provided the goods and services to |
Money Judgment |
Generally 4 years, with certain exceptions for 2
years |
|
Mechanic’s Lien |
Owner of property and the entity you contracted with |
Money judgment that can be collected by foreclosing
on the property that was liened |
File lawsuit 90 days after recording the mechanic’s
lien, which is only valid if the prerequisites are
satisfied |
Payment Bond |
Principal on payment bond ( typically the general
contractor) and the surety issuing the bond |
Money judgment that can be satisfied by payment from
the surety who issued the bond |
Six months after the notice of completion or
cessation is recorded, if none recorded then 6
months after the 60 day period expires from the date
of actual completion |
|
Stop Notice (Private Works) |
Owner, General contractor and lender holding funds |
Money judgment that can be recovered from the funds
withheld in accordance with the stop notice |
File lawsuit 90 days after serving the stop notice,
which is only valid if the prerequisites are
satisfied |
Only certain parties are
able to take advantage of the lien laws. In order to
qualify, the prospective claimant must generally
(1)
perform services, provide labor or provide materials
to the project;
(2)
the services, labor or materials which were supplied
must be used or consumed in the project; and
(3)
the owner or his representative (e.g., general
contractor) must authorize the services or materials.
The Mechanic’s Lien, Stop
Notice and Payment Bond procedures involve three basic
steps:
First Serving a preliminary 20-day notice;
Second Recording the Mechanic’s Lien, serving
the Stop Notice or making the claim on the payment bond; and
Third Filing a lawsuit to: (1) foreclose the
Lien; (2) enforce the Stop Notice, or (3) enforce the claim
against the surety.
Accompanying this article
is a Simplified Private Work Mechanic’s Lien that sets forth
the basic steps for exercising these unique remedies. As
previously stated, if you intend to use these remedies you
must comply precisely with the statutory conditions for
using them. If you are unfamiliar with the requirements, it
is recommended that you attend a seminar on the lien laws.
If you have a specific question about application of the
lien statutes to your particular situation, you should seek
the advice of legal counsel who is familiar with this area
of
SIMPLIFIED PRIVATE
WORK MECHANIC LIEN
AND STOP
NOTICE ACTION GUIDE FOR
PRIVATE
WORK OF IMPROVEMENT
|
Event/Task |
Date |
Action |
Action Completion
Date |
|
Project Commencement Date |
|
|
|
|
First Work Performed By Claimant |
|
If private works: Serve preliminary lien notice on
general, owner and lender within 20 days of
first performing work |
|
|
|
|
If |
|
|
Preliminary Lien Notice Served On owner, general and
lender |
|
|
|
|
Notice of Completion Or Cessation Recorded by Owner |
|
If General Contractor
record lien in |
|
|
|
|
If not General Contractor
record lien in |
|
|
If No Notice of Completion, Date of Actual
Completion |
|
File lien/stop notice within 90 days |
|
|
If payment bond |
|
Mail notice to surety and bond principal (by
certified mail) within 15 days after Notice
of Completion or if a Notice of Completion is
recorded then mail notice within 75 days
after actual completion |
|
|
If Mechanic Lien/ Stop Notice filed/served |
|
If private works, file lawsuit to foreclose within
90 days. If California Public works within 90
days after period in which stop notices must be
served |
|
Back to top of page
HOW TO EXTEND
THE LIFE OF A MECHANICS’ LIEN
By William L. Porter, Attorney at Law
Although the general rule is that an action to foreclose on the
mechanics’ lien must be filed within 90 days after the lien has been
recorded at the County Recorder’s office where the property is
located, it is possible to extend this 90-day deadline. Civil Code
section 3144 describes the means to do so. Section 3144 states:
3144. (a) No lien provided for in this chapter binds any property
for a longer period of time than 90 days after the recording of the
claim of lien, unless within that time an action to foreclose the
lien is commenced in a proper court, except that, if credit is given
and notice of the fact and terms of such credit is recorded in the
office of the county recorder subsequent to the recording of such
claim of lien and prior to the expiration of such 90-day period,
then such lien continues in force until 90 days after the expiration
of such credit, but in no case longer than one year from the time of
completion of the work of improvement.
(b) If the claimant fails to commence an action to foreclose the
lien within the time limitation provided in this section, the lien
automatically shall be null and void and of no further force and
effect.
Note: This “Notice of Credit” document must be signed by the owner
before a notary and properly recorded at the office of the County
Recorder where the property is located. A simple letter from the
owner will not suffice. The recorded Notice of Credit also
will not extend the lawsuit deadline any longer than one year from
the date of actual completion of the work of improvement. It is
recommended that the Notice of Credit be used extremely sparingly.
In most cases it does not result in any real benefit to the claimant
and only delays payment further and/or provides the owner with
additional time to try to determine some means to defeat the
collection efforts of the claimant.
William L. Porter is a principal in Porter Law Group, Inc. in
Sacramento, California. He can be reached at (916) 381-7868.